Monday, July 18, 2011

Decking progress July 18, 2011

Here is the completed east side deck. I finished this before I went into the mountains on the 15th. I started the front deck on the afternoon of the 17th. It looked like I would run out of 2 X 6's. I pulled the extra 16 ft 2 X 6's from the loft that were left over from last year. I purchased 18 more 12 ft 2 X 6's this morning. This should complete the decking.

As I was putting down the decking today I realized I was going to run out of deck screws again. I will need to purchase at least 8 more pounds of screws in the morning if I want to complete the decking tomorrow.

The front deck is coming along very well. Once we are done with the decking, I will install the light cans over the deck and then install the soffits over the deck on both sides.

I should have enough tongue and groove (T&G) boards to complete the soffits. About a third of the T&G I have on hand have been stained and are ready to be installed. Other than a slight problem with the east side TGI's, the soffits should go very fast.

I still have not made up my mind on the color of the siding for the end gables and the dormers. Help!

Recharging in the mountains July 16, 2011


I took a few days off for research. We went into the mountains above Sheridan, MT and saw quite a few different log cabins. Some, like the one I am sitting in front of here were probably built in the late 1800's. Some were built in the early to mid 1900's. A couple were less that 20 years old.

It's interesting to see the different ways they were built. Some have weathered better than others.



We were above the tree lines several times. Here is a picture I took looking across from one mountain to another. We hit a lot of snow in some places. Jim and I tried going across a pass only to be stopped by a field of snow a quarter of a mile wide by at least three miles long. Jim thought it had to be at least 80 feet deep in places.

Time to get back to work!

Wednesday, July 13, 2011

Side decks close to completion July 13, 2011

Today we finished the west side of the deck. This portion is about 52 feet long and 10 feet wide. It was a little tricky getting the last board installed against the base of the house. The sill logs extend beyond the edge of the basement walls.

The second photo shows the progress on the east side deck. This portion of the deck is the same size as the west side. I plan to complete the east side tomorrow and begin the portion of the deck on the front of the house.


The front section of the deck is the final phase for the deck board installation. The dimensions are 36 feet long by 10 feet wide. There are 4 poles I have to scribe out.

I bought a lumber straightener a few weeks ago to help keep the 2 X 6's straight as I screw them down. It appears the longer they stay stacked together, the more bends they develop. I broke the tool today. Triple S in Butte replaced it at no charge. I also had to buy more deck screws. I started out with 42 pounds; I purchased 10 more pounds today.

Once the decking is completed I plan to install and wire in the can lights over the deck. With these completed I can begin installing the soffits over the deck. I will need to get back to tiling the shower at some point very soon.

Sunday, July 10, 2011

Deck in progress july 10, 2011

Here is the deck after the second day of installation. I went into the mountains today on dirt bikes with my cousin so I did not start work until 5 PM. I have a little over 50% of the decking completed on this (east) side. I have lost my hired help for the next three days so I will start the west side tomorrow. Scribing around the logs is the most time consuming so I will get this completed before Jimmy returns on Thursday.

Jimmy has been doing an excellent job cutting the deck boards to length, routing the ends and staining them. When he comes back I will be training him to screw the deck boards down. I found out today that I can easily cut the boards to length using my portable circle saw, which will eliminate a lot of extra handling of the boards.

Tuesday, July 5, 2011

Soffits installed, deck started July 5, 2011


Today I finished installing the soffits on the dormers. It was very difficult to staple the soffits at the very back where the soffit meets the roof. The roof is a 9 - 12 pitch so it was difficult to stay on the roof while I was installing them.



The temperature hit 85 degrees today, the warmest day I've seen in Montana this year. Tony is back this week caulking between the logs with Log Jam.

We began in installing the decking today. It is very time consuming getting the three outer deck boards installed because we have to scribe every board and cut them out with a jig saw before we screw them down. Once the three outer boards are installed, the rest will go very fast; all we have to do is cut them to length, router and stain the end we cut, and screw them down. We will reinstall the 4 X 8 sheets of OSB on the deck top with a couple of screws to protect the surface from damage during the rest of the construction.


I will be moving cattle for Myles Carpenter for the next few days. I will be getting more logs from Myles in return.




Friday, July 1, 2011

Installed soffits on end gables July 1, 2011

I started installing the soffits on the end gables yesterday and finished them up today. Tomorrow I will install the soffits on the dormers. Once the dormer soffits are completed, I will frame out the windows with 2 inch rough cut cedar and the house will be ready for the siding, which I plan to order next week.

I also have to order a bunk of tongue and groove boards to finish the soffits on the sides of the house. These will be stained before I install them. I have 8 angled can lights to install over the covered decks on both sides of the house (4 per side) before I install the soffits. These will be installed and wired next week.

I finished framing out the end of the deck on both sides of the house and installed the last backer blocks at the deck support posts earlier this week. All the 2" by 6" deck planks have been stained. Everything is in place and I am ready to install the deck planking.

Thursday, June 30, 2011

Bathroom in progress June 30, 2011



















Joel Gershenfeld (on the left) and Jim Joyce helped get the bathroom 90% complete on the sheetrock, and to at least 80% complete on the painting. With Joel's help we worked late into the night on the 28th and into the early evening on the 29th to complete the bathroom. We installed the vanity, plumbed in the sink and reinstalled the toilet. We turned on the hot water heater and everything is a go! I'm having a minor problem with a leak at the sink which I will correct by moving the vanity a half inch to the right.

I decided the bathroom could take a rest today so I started installing the soffits on the gable ends. When I went to install the first tongue and groove board I discovered the staple gun I purchased was actually a brad nailer (boxed wrong). Back to the store for an exchange!!!

Tomorrow I will continue with the soffits. When the temperature hits 85 degrees (which is in the forecast for the next 6 days) I will probable begin tiling the shower floor and walls. The basement stays very cool even on the warmest days. We only have 6 more of the 16 foot 2" X 6" planks for the deck left to stain/oil. (173 completed)