Friday, June 24, 2011

Bathroom floor tiled June 24, 2011

Today I removed the toilet in the bathroom and installed the floor tiles. I had to mix the thin set, which I have never done before. In the past I purchased pre-mixed product. I bought a mixer I run with my 1/2' drill. It actually worked very well.

The tile saw I purchased in Butte made the job go smoother with much better cuts. I will grout the tile on Sunday, and install the sheetrock before I reinstall the toilet. The tile for the shower floor will be 6" X 6". The shower wall tiles will be the same size as the bathroom floor tiles; 12" X 12". The shower tiles were shipped today and will arrive in Butte next Tuesday.

Before

After

Thursday, June 23, 2011

Bathroom wiring completed, outside sheeted. June 23, 2011

Today I finished wiring the bathroom lights, outlets and fan. Everything works! I then sheeted the outside of the bathroom and the outside of the mechanical room. It's time to tile!

Wednesday, June 22, 2011

Basement bathroom June 22, 2011

Since my last posting I have the shower ready to tile. I installed the light/fan in the shower; it is ready to be wired in as soon as I pick up the special light switch. I plumbed in the water heater and wired it to the main panel. When I have the shower tiling completed, all I have to do is turn on the breaker and the water valves. This picture shows the water heater and the water manifolds, one for hot and one for cold. I use red PEX for all hot lines, blue for cold.

The manifolds have valves on each outlet. As I add water circuits in the house all I have to do is connect them to the correct manifold and turn the valve.

Tomorrow, after I finish wiring the bathroom, I will begin setting up to install the soffits on the end gables. I purchased a bunk of of 2 X 6's for the deck this week. I have hired a high school student to stain all four sides and the ends. When they are all stained and dry, I will begin installing them.