Monday, July 22, 2013

July 22, 2013 Loft floor nearly completed.



   These two photos show the loft floor about 98% complete. I have two rows left to install. I ran out of 2 X 6's, which I picked up today, and will stain tomorrow. 

   The top log on the far right side in the bottom picture is only about 3 inches above the loft floor level. I will have to install the next wall log on that side before I finish the floor. If I install the last row now, I think it will interfere with the scribing of the next wall log. The last row of 2 X 6's will have to be scribed, and cut to fit with a jigsaw. The first row I installed was also scribed to fit. Note the stairwell in the back!

   Tomorrow we will begin installing the last 6 wall logs.