Saturday, September 3, 2011

Siding end gables September 3, 2011


Yesterday, September 2nd, I started siding the end gables. Fitting the trim around the logs (Top wall logs, purlins and ridgepole) takes a fair amount of time. Once I have the trim installed, the installation of the siding goes pretty fast.

The top picture is the south end. I did as far up as I felt safe. I used the lift cage to lift all my tools up, then I used a ladder to carry the cut siding into the cage. Most of the trim I cut while in the cage using a portable circular saw and a jigsaw. I am caulking the siding as I go so there will be nothing else to do to the siding when I finish the installation.

The second picture shows the progress on the north end. Once I get all I can safely reach by myself, I will get someone to run the lift while I install the upper siding on both ends.

Tony finished the second clear coat on the basement bathroom door, mechanical room door and the trim for both doors. I'll install the trim this coming week.

I started repairing the culvert on the east side of the house. I found I had the wrong size 90 degree pipe. The right one will be in next week.

Thursday, September 1, 2011

Landscaping and sidewalk completed August 3, 2011


Today I placed black plastic sheets under the deck on both sides of the house, then I had help to install 10 yards of small stone over the plastic. The west side is complete. On the east side I am short a small amount of the larger stone.

The picture below shows the sidewalk, and pads for the deck steps, completed. They were poured yesterday and I stripped the forms off this morning. I used the same small rock between the sidewalk and the house, and on the outside of the sidewalk.



Yesterday I finished tiling the shower. Tomorrow I will grout the tile and the shower will be ready to go. I may need to install a shower door.

Once I complete the grout, I will begin installing the trim on the end gables, getting them ready for the siding.



Monday, August 29, 2011

Dormers completed August 29, 2011

Today I finished siding and caulking the dormers. I used a special caulk that matches the color of the siding. I'm done walking on this side of the roof.

Tomorrow I begin siding the south end gable. I'll tackle the toughest one first. The end gables should go pretty fast. The most difficult areas will be where the trim and siding meet the ends of the top wall logs, the ridge poles and the purlins. I'll use the bulls eye scribe to mark the trim and siding and cut them out with a jigsaw.

Sunday, August 28, 2011

Bathroom close to completion, siding Dormers August 28, 2011

This weekend I began installing the corner and window trim and started siding the dormers. Monday I will finish the dormers and begin trimming out the end gables. The interior bathroom doors, shower ceiling and the outside walls have all been painted. Today I hung the doors on the bathroom and mechanical room. I also installed the vanity mirror, the vanity lights and two towel racks. I installed the light switch and outlet covers in the bathroom.