Showing posts with label Basement Shower. Show all posts
Showing posts with label Basement Shower. Show all posts

Wednesday, June 22, 2011

Basement bathroom June 22, 2011

Since my last posting I have the shower ready to tile. I installed the light/fan in the shower; it is ready to be wired in as soon as I pick up the special light switch. I plumbed in the water heater and wired it to the main panel. When I have the shower tiling completed, all I have to do is turn on the breaker and the water valves. This picture shows the water heater and the water manifolds, one for hot and one for cold. I use red PEX for all hot lines, blue for cold.

The manifolds have valves on each outlet. As I add water circuits in the house all I have to do is connect them to the correct manifold and turn the valve.

Tomorrow, after I finish wiring the bathroom, I will begin setting up to install the soffits on the end gables. I purchased a bunk of of 2 X 6's for the deck this week. I have hired a high school student to stain all four sides and the ends. When they are all stained and dry, I will begin installing them.

Wednesday, June 15, 2011

Framing shower and bathroom June 15, 2011




Today I finished framing in the shower and the bathroom. The floor of the shower has been sloped to the drain with cement, Tomorrow I'll install the membrane over the shower floor, secure it at the drain, and cover it with 1 inch of mason cement. When this is completed, I can install the hardiboard on the walls and bench and get set to install tiles.