Friday, July 5, 2013

July 5, 2013 Loft Logs in

 

   Two days ago we finished installing all the loft logs and  capped the main beam on both ends. Yesterday, I started staining until I ran out of stain, then I installed screws through the top of the door and window frames to secure them to the next full log.

   Today, I went to Three Forks and purchased the rest of the logs; 10 wall logs and 2 purlins. I'll stain logs until the roof structure materials arrive on Monday, then I will start prepping TGIs (Rafters) and building blockers to go between the TGIs. As I type this up, the wind is blowing probably close to 40 MPH and it is getting ready to dump a lot of rain!