   Today I finished staining all the logs, inside and out, that have been put on the walls so far. I did forget to complete the two support poles. I also finished framing out the two large garage doors. There are 10 more logs to be installed on the walls, then we will begin the roof system.

   Once we complete the next round of logs, I can install the loft floor, which will be tongue and groove 2 X 6's just like in the house. The only difference is, this time I will stain the bottom of the loft floor 2 X 6's before I install them. This will eliminate overhead staining, and give a more complete coating.

   I also completely stained the 2 purlins and the ridgepole for the roof system. This was much easier to complete before they were installed, again eliminating overhead painting and painting off a ladder. Monday morning we begin installing the rest of the wall logs.